If fabricated structural steel is determined not to fit by 3/8 inches, how should this be resolved?

change the backwall detail

erect the structural steel

issue a field memo

submit an RFI to the designer

When fabricated structural steel does not fit according to the specified dimensions, submitting a Request for Information (RFI) to the designer is the appropriate course of action. This process involves formally asking the designer to clarify or provide guidance on the discrepancies observed.

By using the RFI process, you engage the designer in resolving potential design or fabrication issues that could have arisen. The designer may provide additional details, specifications, or revised information that can rectify the issue at hand. This step ensures that the project adheres to the original design intent while maintaining structural integrity and safety.

Changing design elements, erecting misfit pieces, or issuing field memos may not address the root issue and could lead to further complications down the line. Engaging with the designer through an RFI not only adheres to industry best practices but also helps ensure compliance with all engineering standards.